Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Ideally, we would like to have install the TePLA and commission it before retiring the Branson.
    • Install TePLA on top of Branson table (tool is 29" × 26", table is 40" × 30"); UV ozone and vacuum oven to go under table when Branson is retired.
    • New N₂ line is run up to under the tool, to service TePLA
    • Existing O₂ to Branson can be teed off, then welded after Branson is retired.
    • Use old µEtch pump (already in place) and SS exhaust (if available).
    • Power requirements:  110 V / 60 Hz
  • Glenn Elaschuk is adamant that this install will be easy.

Action items

  •